self Maths Puzzle

Q. The work done by (x-1) men in (x+1) days and the work done by (x+1) men in (x+2) days are in ratio 5:6. Find x?

Read Solution (Total 2)

self Other Question

Q. What is the next number of the following sequence
45, 43, 83, 245, 975, 4869, ?
Q. Harish is thrice as good a workman as Manish and therefore able to finish a piece of work in 60 days less than Manish. Find time in which they can do it together.