self
Government Jobs Exams
Numerical Ability
Time and Work
Q. 2 men & 3 women can finish a piece of work in 10 days, while 4 men can do it in 10 days. How many days will 5 men women take to finish it?
Read Solution (Total 1)
-
- 12 days for 5 women
If 1 day work of Men=1/x & Women=1/y, then
(2/x)+(3/y)=1/10 ---(i) &
4/x=1/10, x=40
Eqn.(i) becomes,(2/40)+(3/y)=1/10, y=60
So 5 women can complete the work in 60/5=12 days - 10 years agoHelpfull: Yes(2) No(0)
self Other Question