Elitmus Exam Numerical Ability Time and Work

A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time?

Read Solution (Total 7)

Elitmus Other Question

did anyone remember the question of data sufficiency ,,question was like that q) what is value of x^3+y^3 1)(x+y)^3 given that (x+y)=4 2) dont remember the statemnt given (x+y)=4 xy=2.. Three persons A,B and C rent the grazing of the park for Rs 570. A put 126 oxen in the park for 3 months, B puts in 162 oxen in the park for 5 months and C puts in 216 oxen in the park for 4 months. What part of rent should B pay?