Time and Work
p alone would take 8 hours more to complete a job than than both p and q would toghter. if q worked alone, he took 9/2 hrs more than p and q would together. what time they take if and q do it together?
Read Solution (Total 3)
-
- let p & q complete in x hr
then p take x+8 hr
q take x+4.5 hr
then (1/x+8)+(1/x+4.5)=1/x
by solving this we get x=6
so they took 6 hr to complete the work - 10 years agoHelpfull: Yes(3) No(1)
- i think its ans is 25/72
- 10 years agoHelpfull: Yes(0) No(4)
- There is formulae for this type of q i.e
[ T(p+q)]^2= T(p)×T(q). [T(p+q)]^2= 8×9/2=36. T(p+q)=+6 because hrs are in +ve - 4 years agoHelpfull: Yes(0) No(0)