Numerical Ability
Time and Work
A,B,C can do some work in 36 days. A and B together can do twice as much work as C alone, and A and C together cand do thrice as much work as B alone. Find the time taken by C to do whole work?
Option
a) 96 days
b) 108 day
c) 120 days
d) 72 days
Read Solution (Total 3)
-
- GIVEN,
1: 1/A+1/B+1/C=1/36
2: 1/A+1/B=2/C
FROM 1 & 2,
1/C=1/108
answer 108 days - 10 years agoHelpfull: Yes(24) No(0)
- (1/A)+(1/B)+(1/C)=1/36
1/A+1/B=2/C
so 1/C=1/108
c=108
- 10 years agoHelpfull: Yes(1) No(0)
- c will take 108 days
- 10 years agoHelpfull: Yes(0) No(3)