16 men can complete a work in 15 days . 24 children can do same work in 20 days . in how many days will eight men and 8 children together complete the work ?
Read Solution (Total 1)
-
- 1 men 1 day work = 1/16*15.
1 children 1 day work = 1/24*20.
now 8 men and 8 children complete the work in = (1/16*15)*8 + (1/24*20)*8 = 1/20;
now work completed by them in 20 days. - 9 years agoHelpfull: Yes(0) No(0)