a man,woman & a boy can do a work in 20 days,30 days & 60 days respectively.how many boys must assist 2 men and 8 women to do the work in 2 days?
Read Solution (Total 1)
-
- it is clear
that job of 1 man = job of 3 boys
job of 1 woman = job of 2 boys
so 2 men = 6 boys
8 women =16 boys
1 boy can do work in 60 days
so 30 boys can do work in 2 days.
2men +8 women = 22 boys
Additional boys reqd = 30-22=8 boys - 13 years agoHelpfull: Yes(19) No(2)