TCS Company Numerical Ability Time and Work

Roja and Edward were working in a courier company. Roja takes 6 hours to pack 32 parcels while Edward takes 5 hours to pack 40 parcels. How long they will take to pack 330 parcels working together ?
a) 24 hours 45 minutes b) 23 hours c) 25 hours 15 minutes d) none of these.

Read Solution (Total 13)

TCS Other Question

There are 4 machines namely P, Q, R and S in a factory. P and Q running together can finish an order in 10 days. If R works twice as P and S works 1/3 as much as Q then the same order of work can be finished in 6 days. Find the time taken by P alone to complete the same order.
a) 11.5 days b) 12.5 days c) 13.5 days d) 14.5 days
Mr.P,Mr.Q and Mr.R takes a project and they can complete in 36 hours , 54 hours and 72 hours respectively. Unfortunately Mr.P met an accident and left from the project 8 hours before the completion while Mr.Q left 12 hours before the completion. Then for how many hours did Mr.r worked?

a) 24
b) 18
c) 42
d) 36