Numerical Ability
Time and Work
Mr.P,Mr.Q and Mr.R takes a project and they can complete in 36 hours , 54 hours and 72 hours respectively. Unfortunately Mr.P met an accident and left from the project 8 hours before the completion while Mr.Q left 12 hours before the completion. Then for how many hours did Mr.r worked?
a) 24
b) 18
c) 42
d) 36
Read Solution (Total 13)
-
- Assume that the project has to be completed in X hours.
So R has worked for X hours.
Since P has left 8 hours before completion, he worked for X - 8 hours and
Q had left 12 hours before, his participation in work is for X - 12 hours.
Therefore (X - 8) + (X - 12) + X = 1(completion of project)
P can complete a project in 36 hours.
In (X - 8) hours P can complete = (X - 8) / 36
Similarly, Q can complete a project in 54 hours.
In (X - 12) hours P can complete = (X - 12) / 54
In X hours R can complete = X / 72
(X - 8) / 36 + (X - 12) / 54 + X / 72 = 1
6 (X - 8) + 4(X - 12) + 3X = 216
13X = 312
X = 24
Hence the required answer is 24 hours. - 10 years agoHelpfull: Yes(69) No(2)
- (x-8)/36+(x-12)/54+x/72=1
12(x-8)+8(x-12)+6x=432
x=24 - 10 years agoHelpfull: Yes(11) No(4)
- let us take lcm of time taken by p,q,r that is 216 work now find per hour work , that is p= 216/36=6 similarly for q=4work per hour and r= 3 work per hour now taking option to satisfy condition takin a that is 24 so for first 12 hour all work togather thats is adding every one per day work
6+4+3= 13 ,13*12 =156 work now after this q left noe p and r work together so 6+3=9 so for next 4 days 9*4=36 noe for rest 8 day only r will work . so 8*3=24 adiing all work 156+36+24=216 so total work = calculated work so this is correct answer . - 10 years agoHelpfull: Yes(9) No(0)
- Assume that the project has to be completed in X hours.
So R has worked for X hours.
Since P has left 8 hours before completion, he worked for X - 8 hours and
Q had left 12 hours before, his participation in work is for X - 12 hours.
Therefore (X - 8) + (X - 12) + X = 1(completion of project)
P can complete a project in 36 hours.
In (X - 8) hours P can complete = (X - 8) / 36
Similarly, Q can complete a project in 54 hours.
In (X - 12) hours P can complete = (X - 12) / 54
In X hours R can complete = X / 72
(X - 8) / 36 + (X - 12) / 54 + X / 72 = 1
6 (X - 8) + 4(X - 12) + 3X = 216
13X = 312
X = 24
Hence the required answer is 24 hours. - 10 years agoHelpfull: Yes(2) No(3)
- Assume that the project has to be completed in X hours.
So R has worked for X hours.
Since P has left 8 hours before completion, he worked for X - 8 hours and
Q had left 12 hours before, his participation in work is for X - 12 hours.
Therefore (X - 8) + (X - 12) + X = 1(completion of project)
P can complete a project in 36 hours.
In (X - 8) hours P can complete = (X - 8) / 36
Similarly, Q can complete a project in 54 hours.
In (X - 12) hours P can complete = (X - 12) / 54
In X hours R can complete = X / 72
(X - 8) / 36 + (X - 12) / 54 + X / 72 = 1
6 (X - 8) + 4(X - 12) + 3X = 216
13X = 312
X = 24
Hence the required answer is 24 hours. - 10 years agoHelpfull: Yes(2) No(0)
- (x-8)/36+(x-12)/54+x/72=1
12(x-8)+8(x-12)+6x=432
x=24 - 9 years agoHelpfull: Yes(1) No(0)
- Let x be the total hour taken by r to complete the work
p 36 - 6 WORK/HOUR
q 54 LCM (216) -4 WORK/HOUR
r 72 -3 WORK/HOUR
here 216 is the total work
p works for (x-8)hours
q works for (x-12)hours
r works for (x)hours
thus
6*(x-8)+4*(x-12)+3*x=216
after solving this equation
we get x=24
hence ans is 24 - 9 years agoHelpfull: Yes(1) No(0)
- 42 is the answer....
- 10 years agoHelpfull: Yes(0) No(19)
- 24 is the ans
- 10 years agoHelpfull: Yes(0) No(1)
- (x-8)/36+(x-12)/54+x/72=1
6(x-8)+4(x-12)+3x=216
6x-48+4x-48+3x=216
13x=312
x=24
ana:a - 10 years agoHelpfull: Yes(0) No(0)
- let xhrs be the time for completion of work
then,p's 1hr work->1/36 & he works for x-8 hrs
q's 1hr work->1/54 & he works for x-12 hrs
r's 1hr work->1/72 & he works for x hrs
(x-8)/36+(x-12)/54+x/72=1
so ans is x= (a) 24
- 10 years agoHelpfull: Yes(0) No(0)
- x-8/36 + x-12/54 + x/72 = 1
so x= 24 hrs - 10 years agoHelpfull: Yes(0) No(0)
- X(1/36+1/54+1/72)+8(1/54+1/72)+1/12(1/36+1/72)=1
SOLVE FOR X
X=4
SO R WORKED FOR 4+8+12=24 HRS
- 9 years agoHelpfull: Yes(0) No(0)