Gate Exam Numerical Ability Time and Work

10 men or 18 children can finish a work in 15 days in how many days 25 men and 15 children can finish the double work

Read Solution (Total 5)

Gate Other Question

16 men can do a piece of work in 16 days four days after they start the work, 8 more persons have joined in . how many more days will be need to complete the rest of the work a,b,c hired a taxi for rs.1040 and used the taxi respectively for 14 hours,16 hours and 22 hours. what is the share of c in the total rent of the taxi