A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
Read Solution (Total 3)
-
- 11days
Work done by A in 1 day = 1/24
Work done by B in 1 day = 1/30
Work done by C in 1 day = 1/40
Let x be the number of days to complete the work
Total work done = 1/24*x + 1/30*x + 1/40*(x-4)
(5x + 4x + 3x -12)/120 = 1
(12x-12) = 120
12x = 132
x = 11
Number of days required to complete work = 11days - 10 years agoHelpfull: Yes(2) No(0)
- One days work of A, B and C = (1/24 + 1/30 + 1/40) = 1/10.
C leaves 4 days before completion of the work, which means only A and B work during the last 4 days.
Work done by A and B together in the last 4 days = (4)(1/24 + 1/30) = 3/10.
Remaining work = 7/10, which was done by A, B and C in the initial number of days.
Number of days required for this initial work = 7 days.
Thus, the total number of days required = 4 + 7 = 11 days. - 10 years agoHelpfull: Yes(0) No(0)
- A's efficiency is 4.16 say 100/24=4.2 ,Similarly B's=100/30=3.3,C's =100/40=2.5
(A+B+C) 1Days work is (4.2+3.3+2.5)=10. 10(A+B+C)*7=70 and 7.5(A+B)*4=30...
11 Days - 10 years agoHelpfull: Yes(0) No(0)