sixty men can build a wall in 40 days.but they begin the work together,5 men quit after 10 day.the time needed to build the wall is
45 49.5 47.5 non
send to my email deepak.rit20@gmail.com
Read Solution (Total 2)
-
- actually 60 men can build a wall in 40 days
suppose same 60 men work for 10 days
then 5 men quit 55 men work for remaining 30 days
then finally remaining work will be 30 * 5 =150 days work
the 55 men can do the 150 days work in 2.72 days
for completion they will take 42.72 days - 10 years agoHelpfull: Yes(4) No(1)
- 60 men 40 days 1 work
60 men 10 days 1/4 work
work left= 1-1/4 = 3/4
55 men 40 days 11/12 work
55 men 1 day 11/480 work
55 men 3/4 work 480/11 *3/4= 32.7 days(approx)
total days= 32.7+10=42.7
non - 10 years agoHelpfull: Yes(3) No(3)