Mr. X has to build a wall 1000 metres long in 50 days. He employs 56 men but at the end of 27 days finds that only 448 metres are built. How many more men must be employed so that the work may be finished in time?
Read Solution (Total 8)
-
- 448 in 27
552 in 23
Men = 448/552 * 23/27 * 56 = 81
Add men = 81-56 = 25. - 10 years agoHelpfull: Yes(36) No(8)
- (men*days*hours)/workdone =(men*days*hours)/workdone
(56*27)/448=(x*23)/552
x=81
81-56=25 - 9 years agoHelpfull: Yes(18) No(1)
- 25 Men
Work done in 27 days=448/1000 =56/125 ,Remaining work=1-(56/125)=69/125
As 56/125 work is done by 56 men in 27 days, so
56 men's 1 day work=56/(125*27) &
1 man's 1 day work= 56/(125*27*56) =1/(125*27)
Now in remaining 50-27= 23 days, work to be completed=69/125
which will be done by 56 men for 23 days & additional 'x' men for 23 days
56 men's 23 days work=(56*23)/(125*27) &
'x' men's 23 days work=23x/(125*27)
[(56*23)/(125*27)]+[23x/(125*27)]=69/125
[(56*23)+(23x)]/27 =69
1288+23x=1863 ,x=25 - 10 years agoHelpfull: Yes(13) No(3)
- at a time,
men proportional to (1/day) and work
so (men*day/work)=constant
by applying this divide problem in two parts
one for 56men 27days 448m work
other part (56+x)men 23days 552m work
and ans is 25
thank you!
- 10 years agoHelpfull: Yes(12) No(0)
- 25 Men
Work done in 27 days=448/1000 =56/125 ,Remaining work=1-(56/125)=69/125
As 56/125 work is done by 56 men in 27 days, so
56 men's 1 day work=56/(125*27) &
1 man's 1 day work= 56/(125*27*56) =1/(125*27)
Now in remaining 50-27= 23 days, work to be completed=69/125
which will be done by 56 men for 23 days & additional 'x' men for 23 days
56 men's 23 days work=(56*23)/(125*27) &
'x' men's 23 days work=23x/(125*27)
[(56*23)/(125*27)]+[23x/(125*27)]=69/125
[(56*23)+(23x)]/27 =69
1288+23x=1863 ,x=25 - 10 years agoHelpfull: Yes(4) No(0)
- 27 DAYS 448 METER 56 MENS
1 MAN BUILS 8METERS IN 27 DAYS
1 MAN BUILS IN 23 DAYS (8/27)*23=6.81 METERS
56 MEN 381.62 METERS
REMAINING =552-381.62=170.37
MORE MEN =170.37/6.81=
25MEN - 9 years agoHelpfull: Yes(2) No(0)
- 56 men builds 448 meters in 27 days
Let N men builds remaining 552 meters in remaining 23 days
(people*days)/work=(people*days)/work
(56*27)/448 = (People*23)/552
27/8 = people/24
people=81
Extra men required = 81 - 56 = 25 - 7 years agoHelpfull: Yes(2) No(0)
- 25
additionally 25 members are required to complete the work in time. - 10 years agoHelpfull: Yes(0) No(1)