TCS
Company
material, labor and maintenance are in the ratio of
4:6:7, the material cost is: 100, what is the total cost?
Read Solution (Total 6)
-
- Let the ratios be 4x,6x and 7x
given the material cost is 100
ie 4x=100
x=25
The labor cost is 6*25=150
The maintenance cost is 7*25=175
Therefore the total cost is 100+150+175 = 425
The answer is 425
- 13 years agoHelpfull: Yes(6) No(0)
- material cost--> 100
4x=100
x= 25
total Cost --> 100+6*25+7*25
=100+150+175
=425 - 13 years agoHelpfull: Yes(1) No(0)
- 4 parts=100
then 17 parts=?
4x=17*100 then x=425 - 13 years agoHelpfull: Yes(0) No(0)
- 4x=100
x=100/4=25
total cost =17*25=425 - 13 years agoHelpfull: Yes(0) No(0)
- material cost is 100
for material 100
labor 6*25=150
maintenance is 7*25=175
toatal is =100+150+175 =425 - 13 years agoHelpfull: Yes(0) No(0)
- 4+6+7=17
x*(4/17)=100
=>x=1700/4
=425 - 12 years agoHelpfull: Yes(0) No(0)