30 girls finish a work in 40 days. after how many 10 girls be permitted to leave so that work gets completed in 46 days ?
Read Solution (Total 2)
-
- 28 days.
30*40 = 1200
30*28 + 20*18 = 840 + 360 = 1200 - 10 years agoHelpfull: Yes(0) No(0)
- Let 30 girls did the work for x days.
It means (46-x) are remained for 20 girls.
Total work is 30 girls * 40 days = 1200 girls-days
So, 30x+(46-x)20 = 1200
x=28 - 10 years agoHelpfull: Yes(0) No(0)