A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. the number of days taken by B to finish the work is:
Read Solution (Total 16)
-
- 15 days.
Let the efficiencies of A and B be '3x' and 'x' respectively.
No of days taken by A and B to complete the work be 'd' and 'd+10' respectively.
So, 3x*d=x*(d+10)
=>3xd=xd+10x
=>2xd=10x
=>2d=10
=>d=5.
The number of days taken by B = d+10=5+10=15.
- 10 years agoHelpfull: Yes(28) No(0)
- Ans:15
1:3
diff=2
a=1,b=3;
b work =3/2*10
=15 - 10 years agoHelpfull: Yes(25) No(0)
- let B takes 3x days and A takes x days.
since B takes 10 days more than A to finish the job,thus
3x=x+10
or,2x=10
or,x=5.
therefore B takes 3x=3*5=15 days to finish the job. - 10 years agoHelpfull: Yes(9) No(0)
- 15 days.
Let B takes x days then A will take (x/3) days as A is 3 times faster.
Moreover A takes 10 days less than what B takes i.e x-10 days
Therefore x-10 =x/3
2x =30
x=15
so B takes 15 days - 10 years agoHelpfull: Yes(6) No(0)
- ans: 15
3A=B
A=B-10
these are the conditions given
solving them
3A=3B-30
3A=B
--------
0=2B-30
--------
2B=30
B=15 - 10 years agoHelpfull: Yes(4) No(0)
- Time taken by A and B to finish the work is A:B=1:3.
So time difference is (3-1)= 2 days.
Therefore, in 2 days difference B takes 3 days
so, in 10 days difference B takes (3/2)*10=15days.
So A will take 5 days to complete the work and B take 15 days to complete the same work.
Ans: B will take 15 days. - 10 years agoHelpfull: Yes(2) No(0)
- A=3B
In terms of work A:B=3:1
In Terms of time A:B=1:3
1:3=(x-10):x
1/3= (x-10)/x
x=15 - 10 years agoHelpfull: Yes(2) No(0)
- taking time ratio a=b/3;
a=b-10
so b=15days - 10 years agoHelpfull: Yes(1) No(0)
- 15 days ........................................
- 9 years agoHelpfull: Yes(1) No(0)
- 25 days
let b takes x days to complete then a takes x/3 daays ie equal to x-10 - 10 years agoHelpfull: Yes(0) No(3)
- 15 days
1/a=1/3b=1/b -10 - 10 years agoHelpfull: Yes(0) No(1)
- A's 1 day work : b's 1 day work = 2:1
B's Can Complete in X days, so A can in X-10 day. therefore
1/x-10=2
x=20 = B can complete work in 20 days - 10 years agoHelpfull: Yes(0) No(1)
- 15 days
work ratio of A and B=3:1
time ratio=1:3
1:3::x-10:x
x=15 - 10 years agoHelpfull: Yes(0) No(2)
- 3 /1 = x/x+10 ( a=3 , b = 1 workdone)
solving x = 15 ( a= x b = x+10 time taken) - 9 years agoHelpfull: Yes(0) No(0)
- let take total work=x
(x/b)-(x/3b)=10
thus, x/b=15 - 8 years agoHelpfull: Yes(0) No(0)
- a:b=1:3
a/b=1/3
b=3a;
b=a+10;
##
3a=a+10
2a=10
a=5
=15 - 4 years agoHelpfull: Yes(0) No(0)