p and a do work in 40 and 25 days.they work together but p left after some days and a finish remaining work in 12 days. after how many days did p leave?
ans:8days
Read Solution (Total 3)
-
- (p+a)'s 1 day work is (1/40+1/25) = 13/200
let they work for x days and after that p left.
Therfore, (p+a)'s x days work togethor = (13/200)*x
Now, Remaining work = 1-(13*x/200) = (200-13*x)/200
This remaining work is to be done by a alone.
We know that a's 1 day work is 1/25
Therefore, a's 12 days work = 12/25
12/25 = (200-13x)/200
x=8 - 10 years agoHelpfull: Yes(2) No(0)
- let p work for x days;
hence, a work for x+12 days;
now
(x/40)+(x+12)/25=1;
x=8; - 10 years agoHelpfull: Yes(2) No(0)
- total time taken by A be x
time taken by A&P x-12
x/25+(x-12)(1/25+1/40)=1
by solving x=256/21 - 10 years agoHelpfull: Yes(0) No(3)