Time and Work
a group of women can finish a piece of work in 50 days in how many day 1/3 number of women be able to find 2/3rd of the work?
Read Solution (Total 3)
-
- Let no. of women is N
N*50/1=(N/3)*?/(2/3)
?= 100 day ans. - 10 years agoHelpfull: Yes(3) No(3)
- Group of women can finish a piece of work in 50 days
lets divide them into 3 equal groups...
then, as per given one group is working and it has to complete 2/3 rd of work.
so the group need to finish other one group's work too.then only 2/3 rd of work will be completed.
so it has to work for another equal amount of time.(50+50)
ANSWER:100 - 9 years agoHelpfull: Yes(1) No(0)
- lets, assume n - be the number of womens, and x - be the days
step 1 ; n=50x
step 2 ; n/3=2*50x/3
therefore n =2*50x ---->100 days - 5 years agoHelpfull: Yes(0) No(0)