12 men and 4 boys togrhter can complete a piece of work in 8 days.The work done by a man in one day is double the work done by a boy in one day.if 10men and 6 boys started working together and after 3days 6 men left and 6 new boys joined,then in how many more days will thw work will be completed?
(1)51/7 days (2) 76/9days (3)43/8days (4)40/7 days (5) 73/12 days