If 20 men can build a wall 56m long in 6 days, then what length
of a similar wall can be built by 35 men in 3 days?
Read Solution (Total 8)
-
- in case 1
no of men =20,length of wall =56 in 6 days
in case 2:
let the length of wall be x
by comapring both cases 1 and 2
56/(20*6)=x/(35*3)
x=49. - 12 years agoHelpfull: Yes(25) No(0)
- for 56m==>20*6=120
so, for 35*3=105==>??=======>56*105/120==>49m - 9 years agoHelpfull: Yes(2) No(0)
- by applying the formula ,
M1 * D1 / W1 = M2 * D2 / W2
M-> MEN , D-> DAY , W-> WORK
therefore,
20 * 6 / 56 = 35 * 3 / W2
120 / 56 = 105 / W2
answer -> W2 = 49. - 8 years agoHelpfull: Yes(2) No(0)
- 20 men ----56m----6 days
1 men ---- 56/20 m----6/20
35 men----56*35/20m -----6*35/20
now,
6*35/20 men-----56*35/20
3 men------(56*35*20*3)/(20*6*35) = 28 - 11 years agoHelpfull: Yes(0) No(10)
- 20Men-56m-6days
35Men-? m -3days
?=(35/20)*(3/6)*56
?=49m - 9 years agoHelpfull: Yes(0) No(0)
- can anyone give the correcr answer??
- 8 years agoHelpfull: Yes(0) No(0)
- by using formula, = men*days/men*days=work/work
- 6 years agoHelpfull: Yes(0) No(0)
- Ans-49
M1D1/W1 =M2D2/W2(FORMULA)
M-MEN
D-DAYS
W-WORK DONE - 6 years agoHelpfull: Yes(0) No(0)