A and B can do a piece of work in 45 days and 40 days respectively. They began to do the work together but A leaves after some days and then B completed the remaining work in 23 days. The number of days after which A left the work was
Read Solution (Total 5)
-
- A does the job in 45 days = 1/45
B does the job in 40 days = 1/40
A & B together completes the job = ?
After A leaves, B completes the remaining job in 23 days.
i.e B's part of job in 23days = 23/40
Remaining part 17/40 is done by A & B together in x no.of days.
i.e (x/45) + (x/40) = 17/40
==> x = 9 days
Soln:
A leaves after 9 days. - 12 years agoHelpfull: Yes(15) No(2)
- (A+B)’s 1 day’s work = 1/45 + 1/40 = 17/360
Now work done by B in 23 days=1 * 23/40= 23/40.
Remaining work = 1-23/40= 17/40
Now, 17/360 work was done by (A+B) in 1 day.
therefore, 17/40 work was done by (A+B) in 360/17 * 17/40 = 9 days. - 9 years agoHelpfull: Yes(0) No(2)
- ans is 9 days for A
- 5 years agoHelpfull: Yes(0) No(0)
- (A+B)'s 1 day's work = 1/45+1/40=17/360
Work done by B in 23 days = 1×23/40=23/40
Remaining work = 1−2340=1740
Now, 17/360 work was done by (A+B) in 1 day.
17/40 work was done by (A+B) in 1×360/17×17/40=9 days
Therefore, A left after 9 days. - 5 years agoHelpfull: Yes(0) No(0)
- x/45 + (x+23)/40 = 1
=> (8x + 9x + 207)/360 = 1
=> 17x = 153
=> x = 9 - 5 years agoHelpfull: Yes(0) No(0)