A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete the work. How many people actually worked on the job to complete it?

Read Solution (Total 11)

IBM Other Question

The monthly incomes of A and B are in the ratio 4 : 5, their expenses are in the ratio 5 : 6. If 'A' saves Rs.25 per month and 'B' saves Rs.50 per month, what are their respective incomes? A, B and C play cricket. A's runs are to B's runs and B's runs are to C's as 3:2. They get altogether 342 runs. How many runs did A make?