Numerical Ability
Time and Work
Four skilled workers do a job in 5 days, and five semi-skilled workers do the same job in 6 days. How many days will it take for two skilled and one semi-skilled worker to do that job?
Read Solution (Total 2)
-
- Ans: 15/2 days
Exp:
4 skilled in 5 day
2 .......... 10 day
5 semi-skilled in 6 days
1 ............... 30 days
2 skilled & 1 semi skilled in one day = 1/10 + 1/30 =2/15 work
hence, 2/15 work in 1 day
so, 1 work will be 15/2 days Ans - 11 years agoHelpfull: Yes(16) No(1)
- Ans is 7 1/2 days
- 12 years agoHelpfull: Yes(5) No(2)