Numerical Ability
Time and Work
Kim can do a work in 3 days while David can do the same work in 2 days. Both of them finish the work together and get Rs.150. What is the share of Kim?
A. Rs.30 B. Rs.60
C. Rs.70 D. Rs.75
Read Solution (Total 4)
-
- the ratio of getting the wage 1/3:1/2=2:3
so Kim will get 2*150/5=60 Rs. - 12 years agoHelpfull: Yes(12) No(1)
- Kim's wages : David's wages = Kim's 1 day's work : David's 1 day's work
= 1/3 : 1/2
= 2 : 3
Kim's share = Rs.(2/5×150)
= Rs.60. - 6 years agoHelpfull: Yes(1) No(0)
- 3+2=5
150/5=50
1day work =10
kim 3 days =30/- - 5 years agoHelpfull: Yes(0) No(1)
- one day work
1/3+1/2=5/6
both will finish the work
6/5days
share of kim is
(6/5*150)/3=60 - 5 years agoHelpfull: Yes(0) No(0)