Four men and three women can do a job in 6 days. When five men and six women work on the same job, the work gets completed in 4 days. How long will a woman take to do the job, if she works alone on it?
Read Solution (Total 6)
-
- 24m+18w=20m+24w
=>1m=3/2w
3(1/3w)+3w=1/6=
>w=54 days - 12 years agoHelpfull: Yes(19) No(2)
- 4m+3w=1/6,5m+6w=1/4 by solving both eqns we get m=1/36
women working days :6 - 13 years agoHelpfull: Yes(10) No(22)
- From the given question
4m+3w=1/6 5m+6w=1/4 by solving two equations we get m=1/36
by that we can have w=1/18.. i.e., amount of work for 1 day alone
and hence amount of total work done in 18 days.... - 12 years agoHelpfull: Yes(6) No(14)
- 24m+18w=20m+24w
=>1m=3/2w
3(1/3w)+3w=1/6=
>w=54 days - 11 years agoHelpfull: Yes(4) No(1)
- 2 equations formed are :
4/x + 3/y =1/6(1/x=work done by a man in 1 day; 1/y = female 1 day's work)
5/x + 6/y =1/4
on solving:-
x=36;y=54
- 11 years agoHelpfull: Yes(3) No(3)
- How you got m=1/36.This no body explained.complete step wise solution is required for beginners.
- 10 years agoHelpfull: Yes(3) No(0)