A private limited company entrusts works to 20 men, working 12 hours a day. This group can complete the work in 24 days. The company now wants to entrust twice the work to 60 men working 4 hours a day. Assume that 2 men of the first group do as much work in one hour as 3 men of second group do in 1 ½ hours. How many number of days will the second group of men take to complete this work?

a) 108 days b)120 days c)124 days d)81 days

Read Solution (Total 1)

Wipro Other Question

Adhvaith can do a certain work in 30 days. Kashyap can do same work in 25 days. Adhvaith started the work and worked for 9 days. Kashyap came and joined to do the work from the 10th day. How many more days would they have taken together to complete the work?

a)10 3/11 days b)11 2/11 days c) 9 6/11 days d) 8 2/11 days
Three persons Manmohan, Anna And Sushma working together, can do a job in X hours. When working alone, Manmohan needs an additional six hours to do the job; Anna, working alone needs an additional hour and Sushma working along needs X additional hours. What is the value of X?

a)2/3 b)3/2 c)11/12 d)2