If 10 men can do a work in 4 days, in how many days can 8 men do it?

a)7 days
b)5 days
c)8 days
d)6 days

Read Solution (Total 2)

Wipro Other Question

In what ratio must water to be mixed with milk to gain 20% by selling the mixture at cost price? A wall is built by 17 men in 24 days. In how many days can 18 men do the work if hours per day are reduced in the ratio 5:4?

a)29.75 days
b)28.33 days
c)30.33 days
d)35.25 days