Time and Work
If 10 men can do a work in 4 days, in how many days can 8 men do it?
a)7 days
b)5 days
c)8 days
d)6 days
Read Solution (Total 2)
-
- ans: 5 days
- 10 years agoHelpfull: Yes(1) No(1)
- 10 men can do a work in= 1/4 days
1 men can do a work in=1/(10*4)=1/40 days
so 8 men can do a work in 8/40=1/5
ie 5 days - 10 years agoHelpfull: Yes(1) No(0)