Wipro Company Numerical Ability Time and Work

If 8 men and 6 boys can dig a well in 2 days, and 6 men and 2 boys can do it in 3 days, how long will 5 men and 3 boys take to do it?

a)4.33
b)4
c)3
d)3.33

Read Solution (Total 2)

Wipro Other Question

If 15 men or 24 women or 36 boys can do a work in 12 says working 8 hours a day, how many men should work together with 12 women and 6 boys to do a piece of work in times the earlier one, in 30 days working 6 hours a day?

a)10
b)8
c)4
d)14
Mr. X has to build a wall 1000 meters long in 50 days. He employs 56 men but at the end of 27 days finds that only 448 meters are built. How many more men must be employed so that the work may be finished in time?

a)58
b)81
c)38
d)25