Time and Work
If 20 men take 30 days to complete a job. In how many days can 25 men complete the job?
a)28 days
b)24 days
c)36 days
d)20 days
Read Solution (Total 2)
-
- b)24 days
If 20 men take 30 days to complete a job.
25 men can complete the job in 30*20/25 = 24 days...... option b) - 13 years agoHelpfull: Yes(3) No(0)
- b)24
work always remains constant as no of people is inversely proportional to time taken
20*30=25*x
x=24 - 12 years agoHelpfull: Yes(1) No(0)