Wipro Company Numerical Ability Time and Work

A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one,in 24 days working 8 hours a day?
a)24 men
b)29 men
c)20 men
d)30 men

Read Solution (Total 2)

Wipro Other Question

Fifteen men take 10 days to complete a job working 12 hours a day. How many hours a day should 10 men work to complete the job in 20 days?
a>20 days
b>8 days
c>9 days
d>10 days
A can do a piece of work in 9 days. B can do the same in 12 days. In how many days can the work be completed if A and B work together?
a) 5 1/9 days
b) 5 1/4 days
c) 5 1/3 days
d) 5 1/7 days