Anil and Amit can complete a job in 12 days working together. Amit alone can complete it in 16 days. Both of them worked together for 4 days and then Amit left. How long will Anil take to complete the remaining work?
a>30 days
b>47 days
c>32 days
d>24 days
Read Solution (Total 2)
-
- (Anil+Amit)'s one day work is 1/12
They worked for 4 days and hence they must have completed 4*1/12=1/3 work
The remaining work has to be completed by ANIL=1-1/3=2/3 work
Now, ANIL's one day work =1/12-1/16=1/48
He can complete the work in 48 days
For one work, Anil can complete in 48 days
For2/3 work, Anil can complete in 48*2/3=32 days(option C) - 12 years agoHelpfull: Yes(0) No(0)
- c)32 days
Anil alone can complete the work in 1/12-1/16=1/48
worked for 4 days=4/48+4/16=16/48=1/3
remaining work=2/3
Anil will have to work for 32 days
32/48=2/3 - 12 years agoHelpfull: Yes(0) No(0)