Wipro Company Numerical Ability Time and Work

A can do a piece of work n 7 days of 9 hours each and B alone can do it in 6 days of 7 hours each. How long will they take to do it working together 8 2/5 hours a day?

Read Solution (Total 2)

Wipro Other Question

A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same job? X can do ΒΌ of a work in 10 days, Y can do 40% of work in 40 days and Z can do 1/3 of work in 13 days. Who will complete the work first?