Ravi and manish can do pieace of work in 16 and 20 days respectevey . how long it will take to finish the work if manish
replaced by sanjay after 2 days .Given sanjay and manish finish work togetherin 12days.

(a) 7.8 (b) 10.1 (c) 8 (d) 9.21