Wipro Company Numerical Ability Time and Work

A does 4/5 of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

Read Solution (Total 4)

Wipro Other Question

X and Y can do a piece of work n 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of work. How long did the work last? A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of work finished by C in 2 days. If they get Rs 1500 for the whole work, the daily wages of B and C are?