Wipro
Company
Numerical Ability
Time and Work
A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many boys must assist 1 man and 1 woman to complete the job in ¼ of a day?
(a). 1 (b). 4 (c). 19 (d). 41
Read Solution (Total 2)
-
- (1 man + 1 woman)'s 1 days work = 1/3+1/4=7/12
Work done by 1 man and 1 women n 1/4 day=((7/12)*(1/4))=7/48
Remaining work= 1- 7/48= 41/48
Work done by 1 boy in ¼ day= ((1/12)*(1/4)) =1/48
Therefore, Number of boys required= ((41/48)*48)= 41
So ans is (d) - 12 years agoHelpfull: Yes(7) No(1)
- Option D
Explanation:
(1 man + 1 woman)'s 1 day work = (1/3 + 1/4) = 7/12 Work done by 1 man and 1 woman in 1/4 day = (7/12 * 1/4) = 7/48
Remaining work = (1 - 7/48) = 41/48
Work done by 1 boy in 1/4 day = ( 1/12 * 1/4) = 1/48
Number of boys required = 41/48 * 41 = 41. - 8 years agoHelpfull: Yes(0) No(1)