Wipro Company Numerical Ability Time and Work

Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. Sixteen adults left and four children joined them. How many days will they take to complete the remaining work?
(A) 3 (B) 4 ( C) 6 (D) 8

Read Solution (Total 2)

Wipro Other Question

12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days.
(A) 15 (B) 18 (C) 22 (D) data inadequate
Sixteen men can complete a work in twelve days. Twenty four children can complete the same work in 18 days. 12 men and 8 children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
(A) 2 days (B) 4 days ( C) 6 days (D) 8 days