4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
(A) 35 days (B) 40 days ( C) 45 days (D) 50 days
Read Solution (Total 4)
-
- 32M + 48W = 30M + 70W
2M = 22W
1M = 11W
4 men and 6 women = 50W
10 Women =
so,
4 men and 6 women can complete a work in 8 days,
10 women = ????
50 * 8 / 10
==> 400/10
40 days
- 12 years agoHelpfull: Yes(7) No(4)
- 40 days
4m+6w=1/8
3m+7w=1/10
- 12 years agoHelpfull: Yes(2) No(4)
- 40 days
4m+6w=1/8
3m+7w=1/10
solving the equation gives w=400
then 10w=10/400=1/40
ans is 40 days.. - 10 years agoHelpfull: Yes(2) No(1)
- 40 day
answer:(b)40 - 9 years agoHelpfull: Yes(0) No(0)