Wipro
Company
A and B complete a piece of work in 10 days. B and C in 12 days and C and A in 15 days. All the three of them started working and then B left after 4 days. C left 3 days after that and then immediately B joined A again to complete the remaining work. In how many days was the work completed?
Read Solution (Total 1)
-
- 7 5/6 days total..
- 10 years agoHelpfull: Yes(0) No(0)