3 men and 5 women can complete a work in 12 days, which 5 men and 12 women can complete in 6 days. In how many days can 4 men and 4 women complete the same work?

Read Solution (Total 4)

Wipro Other Question

P and Q agreed to complete a job in 15 days for $6200. P can complete the same job in 50 days and Q in 30 days. They had to take R to complete the work in time. Find R's share in the money earned by them. A is 80 % more efficient than B who is 60% more efficient than C. A takes 40 days less than B to complete a work. A starts the work and works for 25 days and then B takes over. B then work for the next 30 days and then stops. In how much more time can C complete the remaining work?