25 men take 25 days to construct a wall 10 meter high. How many men would be required to construct a similar wall which is 8 meter high, if it is planned that the work would be completed in 10 days?

Read Solution (Total 1)

Wipro Other Question

20 cows and 40 goats can be kept for 10 days for $460. What would be the cost of keeping 50 cows and 30 goats for 12 days if the cost of keeping 5 goats is the same as cost of keeping 1 cow? P can complete a piece of work in 20 days and Q in 30 days. P worked alone for 4 days and then Q completed the remaining work along with R in 18 days. In how many days can R working alone complete the work?