Numerical Ability
Time and Work
25 men take 25 days to construct a wall 10 meter high. How many men would be required to construct a similar wall which is 8 meter high, if it is planned that the work would be completed in 10 days?
Read Solution (Total 1)
-
- m1*d1/w1=m2*d2/w2
25*25/10=x*10/8
so solving we get, x=50 - 12 years agoHelpfull: Yes(1) No(0)