If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in how many days?
A. 1 B.
7
2
C. 7 D. 49
Read Solution (Total 2)
-
- (men*day*hour)/work done
(M1*D1*h1)/w1 = (M2*d2*H2)/W2
(7*7)/7 = (1*d2)/1
d2=7 - 8 years agoHelpfull: Yes(1) No(0)
- Let the required number days be x.
Less spiders, More days (Indirect Proportion)
Less webs, Less days (Direct Proportion)
Spiders 1 : 7 :: 7 : x
Webs 7 : 1
1 x 7 x x = 7 x 1 x 7
x = 7. - 10 years agoHelpfull: Yes(0) No(1)