CSC Company Numerical Ability Time and Work

39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?

A. 10 B. 13
C. 14 D. 15

Read Solution (Total 4)

CSC Other Question

In a dairy farm, 40 cows eat 40 bags of husk in 40 days. In how many days one cow will eat one bag of husk?

A. 1 B. 1/40
C. 40 D. 80
A fort had provision of food for 150 men for 45 days. After 10 days, 25 men left the fort. The number of days for which the remaining food will last, is:

A.29 1/5 B.37 1/4
C. 42 D. 54