Syntel Company Numerical Ability Time and Work

A certain number ofmen complete a piece of work in 45 days. If there were 5 men more, the work could be finished in 9 days less. How many men were originally there?
(a) 30
(b) 15
(c) 25
(d) 20

Read Solution (Total 2)

Syntel Other Question

6 men finish one-fourth work in 2 days. The number of additional men required for finishing the same work in 2 days is.
(a) 18 men
(b) 24 men
(c) 28 men
(d) 14 men
10 workers can make 15 boxes in 6 days, how many boxes will 12 workers make in 3 days.
(a) 10
(b) 9
(c) 6
(d) 8