If 8 men working 9 h a day can reap a field in 24 days, in how many days will 12 men reap the field, working 6 h a day?
(a) 24 days
(b) 20 days
(c) 28 days
(d) 16 days

Read Solution (Total 1)

Syntel Other Question

If 36 persons consume 180 kg of rice in 12 days, in how many days will 42 persons consume 105 kg of rice?
(a) 6 days
(b) 8 days
(c) 4 days
(d) 9 days
If 10 men working 8 h a day can do a piece of work in 12 days, then how many men working 10 h a day can do the work in 16 days?
(a) 10
(b) 5
(c) 6
(d) 8