Numerical Ability
Time and Work
If 12 machines working 7 h a day can finish a work in 18 days, in how many days will 16 machinesworking 9 h a day finish twice the work?
(a) 21 days
(b) 18 days
(c) 24 days
(d) 16 days
Read Solution (Total 2)
-
- 2*(12*7*18)=16*9*d
=>d=21 - 10 years agoHelpfull: Yes(4) No(0)
- 21 days required
- 9 years agoHelpfull: Yes(0) No(0)