A work in 12 days b in 15 days. Find the no of days if they work on alternate days.
Read Solution (Total 2)
-
- 13(1/4)days
- 11 years agoHelpfull: Yes(4) No(0)
- 11(1/4)days...
It came from (1/12)+(1/15)
LCM of 12 and 15 is 60
from that combination of 4&5 is 9 its count as 2
then totally it got as 10days and one 5 day is 11days
and remaining is 1/4
totally 11(1/4)days - 12 years agoHelpfull: Yes(0) No(4)