36 men can complete a work in 18 days.In how many days will 27 men complete same work
a.24 days
b.12 days
c.30 days
d.42 days
Read Solution (Total 1)
-
- a. 24 days
1 man, 1 day work= 1/(18*36)
27 men, 1day work=27/(18*36) =1/24
So 27 men will complete the work in 24 days - 10 years agoHelpfull: Yes(0) No(0)