a contract was signed to complete a job in 30 days. after how many days can 5 men leave then so that the job can be completed in 35 days
Read Solution (Total 1)
-
- It will depend on no of men employed initially.
If no of men used initially is x, then after (35-x) days 5 men can leave so that the job can be completed in 35 days.
If 25 men are employed initially, then
affter 10 days , 5 men can leave and then balance 20 persons can complete job in 25 days ( total 35 days). - 13 years agoHelpfull: Yes(4) No(1)