MAQ Company Numerical Ability Time and Work

A contractor agreed to finish the work in 150 days,employed 70 men each working 8 hours daily.After 90 days only 2/7th of the work completed.Increasing the no.of men by x each working now for 10 hours daily.The work can be completed in time ?Find X
a.100
b.110
c.150
d.190