A and B undertook a work for Rs. 11,500. When they worked together A got Rs. 2,300 less than B and A takes 7 days more than B, when they work individually. In how many days A and B working together can do the whole work ?
Let A got Rs. x, then B Rs. (x+2300), then x + (x+2300)=11500
⇒ x=4600
Thus A got Rs. 4600 and B Rs. 6900 according to their share in work.
.'. Efficiency of A and B = 4600 : 6900 = 2 : 3
Ratio of number of days to complete the work by A and B = 1/2 : 1/3 = 3 : 2
Given, A takes 7 days more than B, so 3a - 2a=7 ⇒ a=7
Thus individually A takes 21 days and B takes 14 days
1 day's work of A and B = 1/21 + 1/14 = 5/42
Hence, A and B together can complete the work in 42/5 = 8⅖ days.